VANCOUVER, BC, Sept. 18, 2020 /CNW/ – SSR Mining Inc. (“SSR Mining” or the “Company”) (NASDAQ: SSRM) (TSX: SSRM) (ASX: SSR) announces updated full year 2020 outlook following the successful completion of the merger of equals transaction with Alacer Gold Corp. (“Alacer”) on September 16, 2020 and reflecting the COVID-19 related impacts to operations at Seabee and Puna. The Company expects to produce, on a consolidated basis, 680,000 to 760,000 gold equivalent ounces from its four operating mines at consolidated all-in sustaining costs (“AISC”) of $965 to $1,040 per ounce.” data-reactid=”12″ type=”text”>DENVER and VANCOUVER, BC, Sept. 18, 2020 /CNW/ – SSR Mining Inc. (“SSR Mining” or the “Company”) (NASDAQ: SSRM) (TSX: SSRM) (ASX: SSR) announces updated full year 2020 outlook following the successful completion of the merger of equals transaction with Alacer Gold Corp. (“Alacer”) on September 16, 2020 and reflecting the COVID-19 related impacts to operations at Seabee and Puna. The Company expects to produce, on a consolidated basis, 680,000 to 760,000 gold equivalent ounces from its four operating mines at consolidated all-in sustaining costs (“AISC”) of $965 to $1,040 per ounce.

Rod Antal, President and CEO said, “The completion of the merger between SSR Mining and Alacer has created one of the premier free cash flow generators in the sector with a number of near term, value enhancing catalysts on the horizon. Despite the COVID-19 related challenges, our full year 2020 outlook demonstrates the strength and resilience of the Company’s diversified operational base. We anticipate a strong finish to the year, particularly in the fourth quarter, as Çöpler and Marigold continue to operate and deliver uninterrupted and Seabee and Puna return to normal operations. We are currently focused on completing our integration efforts and assessing our extensive growth and development portfolio. The upcoming Çöpler technical report in the fourth quarter will be the first step in this process and will begin to define our low capital intensity growth pipeline within the Çöpler District.”” data-reactid=”13″ type=”text”>Rod Antal, President and CEO said, “The completion of the merger between SSR Mining and Alacer has created one of the premier free cash flow generators in the sector with a number of near term, value enhancing catalysts on the horizon. Despite the COVID-19 related challenges, our full year 2020 outlook demonstrates the strength and resilience of the Company’s diversified operational base. We anticipate a strong finish to the year, particularly in the fourth quarter, as Çöpler and Marigold continue to operate and deliver uninterrupted and Seabee and Puna return to normal operations. We are currently focused on completing our integration efforts and assessing our extensive growth and development portfolio. The upcoming Çöpler technical report in the fourth quarter will be the first step in this process and will begin to define our low capital intensity growth pipeline within the Çöpler District.”

June 30, 2020, the combined cash balances were $703 million and debt balances were $475 million.(6) Production for the second half of the year is expected to be 55% to 60% weighted towards the fourth quarter due to both Seabee and Puna ramping up operations in the third quarter following COVID-19 shutdowns, stacking of higher-grade ounces later in the year at Marigold, and higher processed grades during the fourth quarter at Çöpler in line with the mine plan.” data-reactid=”23″ type=”text”>Based on the financial statements of each of SSR Mining and Alacer at June 30, 2020, the combined cash balances were $703 million and debt balances were $475 million.(6) Production for the second half of the year is expected to be 55% to 60% weighted towards the fourth quarter due to both Seabee and Puna ramping up operations in the third quarter following COVID-19 shutdowns, stacking of higher-grade ounces later in the year at Marigold, and higher processed grades during the fourth quarter at Çöpler in line with the mine plan.

In addition to the impact of higher anticipated fourth quarter production, free cash flow generation is also expected to be heavily weighted to the fourth quarter due to the timing of the following expenditures in the third quarter:

September 16, 2020. Therefore, Çöpler will have limited contribution to SSR Mining’s third quarter financial results with full contribution commencing in the fourth quarter.” data-reactid=”33″ type=”text”>SSR Mining will consolidate the operational and financial results of Çöpler commencing from the Alacer transaction closing date of September 16, 2020. Therefore, Çöpler will have limited contribution to SSR Mining’s third quarter financial results with full contribution commencing in the fourth quarter.

$25 to $30 million. The combined share-based compensation for 2020 is forecast to total $20 to $25 million as a result of the strong share price performance.” data-reactid=”34″ type=”text”>Combined G&A expenditures for 2020 are forecast to total $25 to $30 million. The combined share-based compensation for 2020 is forecast to total $20 to $25 million as a result of the strong share price performance.

June 30, 2020 at mine site AISC of $744 per ounce.” data-reactid=”36″ type=”text”>Gold production from Çöpler was 167,212 ounces through June 30, 2020 at mine site AISC of $744 per ounce.

$710 to $760 per ounce. Mine site AISC are higher than original Alacer guidance mainly due to the impact of higher gold prices on royalty costs and the announced increase to government royalty rates in Turkey in early September 2020.” data-reactid=”37″ type=”text”>The 2020 Çöpler production outlook is unchanged, with gold production expected to be 310,000 to 360,000 ounces. Mine site AISC are forecast to be $710 to $760 per ounce. Mine site AISC are higher than original Alacer guidance mainly due to the impact of higher gold prices on royalty costs and the announced increase to government royalty rates in Turkey in early September 2020.

$40 million, which includes ongoing construction of the tailings storage facility (“TSF”) lifts, construction of the first approximate six million tonne heap leach pad expansion, oxygen plant lease payments and for optimization work on the sulfide plant. Growth capital expenditures are planned to total $40 million, which includes capital for accelerating construction of the TSF, expected construction of the flotation plant, work on the additional approximate 20 million tonne heap leach pad expansion and for other growth initiatives, including the Çöpler District Technical Report (“Technical Report”). Capitalized stripping is expected to be $2 million for the full year. With the ongoing oxide exploration success in the district, the 2020 exploration spend is forecast to be $17 million.” data-reactid=”38″ type=”text”>Sustaining capital expenditures are planned to total $40 million, which includes ongoing construction of the tailings storage facility (“TSF”) lifts, construction of the first approximate six million tonne heap leach pad expansion, oxygen plant lease payments and for optimization work on the sulfide plant. Growth capital expenditures are planned to total $40 million, which includes capital for accelerating construction of the TSF, expected construction of the flotation plant, work on the additional approximate 20 million tonne heap leach pad expansion and for other growth initiatives, including the Çöpler District Technical Report (“Technical Report”). Capitalized stripping is expected to be $2 million for the full year. With the ongoing oxide exploration success in the district, the 2020 exploration spend is forecast to be $17 million.

An updated Technical Report is planned to be released in the fourth quarter of 2020. The Technical Report will include:

  • Ardich preliminary development plans
  • Updated performance expectations of the Çöpler sulfide plant
  • Economic and operating impact of the proposed flotation circuit
  • Opportunities for tailings storage expansion

$15 million. The flotation circuit is anticipated to increase the gold and sulfide sulfur grades processed through the autoclaves (increasing autoclave and oxygen utilization), reduce unit costs, and increase sulfide plant throughput and gold production.” data-reactid=”49″ type=”text”>Detailed engineering for the proposed flotation circuit is underway and the construction decision remains subject to final Board and other approvals once the technical work is complete. If approved, the flotation circuit commissioning is targeted in the first half of 2021. The preliminary capital estimate for the proposed flotation circuit is approximately $15 million. The flotation circuit is anticipated to increase the gold and sulfide sulfur grades processed through the autoclaves (increasing autoclave and oxygen utilization), reduce unit costs, and increase sulfide plant throughput and gold production.

With respect to the COVID-19 pandemic, Çöpler continues to operate uninterrupted. However, COVID-19 restrictions and the diversion of resources to manage the pandemic have delayed improvement initiatives which had an impact on operational performance. Proactively sending home older staff and those with existing health conditions also had an impact on mining operations through a shortfall of mine operators. This contributed to a decision in the first half of 2020 to adopt a revised mine plan to diversify ore sources.

June 30, 2020 at mine site AISC of $1,319 per ounce.” data-reactid=”52″ type=”text”>Gold production from Marigold was 108,366 ounces through June 30, 2020 at mine site AISC of $1,319 per ounce.

$1,170 to $1,230 per ounce. Mine site AISC are higher than the original SSR Mining guidance mainly due to the impact of higher gold prices on royalty costs.” data-reactid=”53″ type=”text”>The 2020 Marigold production outlook is unchanged, with gold production expected to be 225,000 to 240,000 ounces. Mine site AISC are forecast to be $1,170 to $1,230 per ounce. Mine site AISC are higher than the original SSR Mining guidance mainly due to the impact of higher gold prices on royalty costs.

$55 million, which includes the construction of a new leach pad and the purchase of two new haul trucks. Capitalized stripping is expected to be $25 million for the full year due to stripping of upper portions of the next phase within the Mackay pit. The 2020 exploration spend is anticipated to be $16 million, focusing on expanding oxide Mineral Resources across the Marigold, Valmy, and Trenton Canyon properties, as well as discovery of higher-grade sulfides at Trenton Canyon. The Marigold exploration spend has increased from the original SSR Mining guidance due to the success of the exploration program through the first half of the year.” data-reactid=”54″ type=”text”>Sustaining capital expenditures are planned to total $55 million, which includes the construction of a new leach pad and the purchase of two new haul trucks. Capitalized stripping is expected to be $25 million for the full year due to stripping of upper portions of the next phase within the Mackay pit. The 2020 exploration spend is anticipated to be $16 million, focusing on expanding oxide Mineral Resources across the Marigold, Valmy, and Trenton Canyon properties, as well as discovery of higher-grade sulfides at Trenton Canyon. The Marigold exploration spend has increased from the original SSR Mining guidance due to the success of the exploration program through the first half of the year.

With respect to the COVID-19 pandemic, Marigold continues to operate uninterrupted. The mine continues to work with national and local authorities in accordance with applicable regulations and remains vigilant with respect to on-site specific protocols to protect the health and safety of our employees and stakeholders.

June 30, 2020 at mine site AISC of $982 per ounce.” data-reactid=”57″ type=”text”>Gold production from Seabee was 29,521 ounces through June 30, 2020 at mine site AISC of $982 per ounce.

$770 to $820 per ounce.” data-reactid=”58″ type=”text”>In 2020, Seabee is expected to produce 80,000 to 90,000 ounces of gold at mine site AISC of $770 to $820 per ounce.

$15 million which includes mining equipment, underground infrastructure and tailings facility expansion. Investment in the tailings facility expansion is expected to be completed in 2021. Growth capital expenditures are planned to total $4 million, which includes phase two of the TSF expansion and development work to access the Santoy Gap Hanging Wall zone. Capitalized development is expected to be $10 million for the full year to support higher mining rates. The 2020 exploration spend is anticipated to be $9 million with a focus on expansion and definition of the Santoy Gap Hanging Wall and surface drill programs at the Seabee and Fisher properties following up on targets identified in 2019.” data-reactid=”59″ type=”text”>Sustaining capital expenditures are planned to total $15 million which includes mining equipment, underground infrastructure and tailings facility expansion. Investment in the tailings facility expansion is expected to be completed in 2021. Growth capital expenditures are planned to total $4 million, which includes phase two of the TSF expansion and development work to access the Santoy Gap Hanging Wall zone. Capitalized development is expected to be $10 million for the full year to support higher mining rates. The 2020 exploration spend is anticipated to be $9 million with a focus on expansion and definition of the Santoy Gap Hanging Wall and surface drill programs at the Seabee and Fisher properties following up on targets identified in 2019.

March 2020 and limited underground development and ore mining operations re-commenced in June 2020. Ore extraction and development rates ramped up through July and milling operations at Seabee commenced in early August. Milling operations re-commenced with an ore stockpile providing mill operating flexibility relative to mine extraction. Mill throughput is anticipated to average over 1,200 tonnes per operating day for the balance of 2020. The restart sequencing and ongoing prioritization of activities at Seabee maintain the flight and camp operations within the determined health and safety protocols.” data-reactid=”60″ type=”text”>With respect to the COVID-19 pandemic, Seabee operations were suspended in March 2020 and limited underground development and ore mining operations re-commenced in June 2020. Ore extraction and development rates ramped up through July and milling operations at Seabee commenced in early August. Milling operations re-commenced with an ore stockpile providing mill operating flexibility relative to mine extraction. Mill throughput is anticipated to average over 1,200 tonnes per operating day for the balance of 2020. The restart sequencing and ongoing prioritization of activities at Seabee maintain the flight and camp operations within the determined health and safety protocols.

June 30, 2020 at mine site AISC of $16.72 per ounce.” data-reactid=”62″ type=”text”>Silver production from Puna was 2.1 million ounces through June 30, 2020 at mine site AISC of $16.72 per ounce.

$15.00 to $17.00 per ounce.” data-reactid=”63″ type=”text”>In 2020, Puna is expected to produce 4.9 to 5.3 million ounces of silver at mine site AISC of $15.00 to $17.00 per ounce.

$15 million, principally focused on maintenance of the mine, mill and power generating equipment. Growth capital expenditures are planned to total $6 million to replace contracted ore transportation as the operation focuses on lowering unit costs. Capitalized stripping is expected to be $7 million for the full year.” data-reactid=”64″ type=”text”>Sustaining capital expenditures are planned to total $15 million, principally focused on maintenance of the mine, mill and power generating equipment. Growth capital expenditures are planned to total $6 million to replace contracted ore transportation as the operation focuses on lowering unit costs. Capitalized stripping is expected to be $7 million for the full year.

March 2020. Puna returned to production late in the second quarter with mining, hauling and milling all re-commencing operations. Travel protocols and restrictions within Argentina and the province of Jujuy remain in place and infection rates have escalated, causing impacts to operations. During the third quarter, Puna has had to reduce and suspend operations sporadically to manage camp occupancy, conduct testing and reduce transmission risk. Strict protocols remain in place to manage COVID risk within the camp and operation.” data-reactid=”65″ type=”text”>With respect to the COVID-19 pandemic, Puna operations were suspended in March 2020. Puna returned to production late in the second quarter with mining, hauling and milling all re-commencing operations. Travel protocols and restrictions within Argentina and the province of Jujuy remain in place and infection rates have escalated, causing impacts to operations. During the third quarter, Puna has had to reduce and suspend operations sporadically to manage camp occupancy, conduct testing and reduce transmission risk. Strict protocols remain in place to manage COVID risk within the camp and operation.

Mexico, $5 million is expected to be spent in 2020 as part of a program to extend an existing decline to provide drill access to the underground Mineral Resources. An improved geological model from work completed in 2019 indicates strong potential to better define known, high-grade mineralized veining associated with steeply dipping rhyolite dyke contacts. Extending the underground ramp provides access for tighter spaced drilling at better orientations to test the rhyolite dykes and veins for continuity. If infill drilling confirms the continuity of high-grade mineralized structures, there would be potential to enhance the grades of existing Mineral Resources. The start of the decline development was delayed due to COVID-19 restrictions and is now anticipated to begin during the fourth quarter of 2020.” data-reactid=”67″ type=”text”>At the Pitarrilla project, located in Mexico, $5 million is expected to be spent in 2020 as part of a program to extend an existing decline to provide drill access to the underground Mineral Resources. An improved geological model from work completed in 2019 indicates strong potential to better define known, high-grade mineralized veining associated with steeply dipping rhyolite dyke contacts. Extending the underground ramp provides access for tighter spaced drilling at better orientations to test the rhyolite dykes and veins for continuity. If infill drilling confirms the continuity of high-grade mineralized structures, there would be potential to enhance the grades of existing Mineral Resources. The start of the decline development was delayed due to COVID-19 restrictions and is now anticipated to begin during the fourth quarter of 2020.

San Luis ” data-reactid=”68″ type=”text”>San Luis

San Luis project, located in Peru, $2 million is expected to be spent in 2020 to commence a detailed mapping program in the area of the existing high-grade gold-silver Mineral Reserves and Resources. Subject to the lifting of travel restrictions in Peru related to COVID-19, work is anticipated to begin during the fourth quarter of 2020.” data-reactid=”69″ type=”text”>At the San Luis project, located in Peru, $2 million is expected to be spent in 2020 to commence a detailed mapping program in the area of the existing high-grade gold-silver Mineral Reserves and Resources. Subject to the lifting of travel restrictions in Peru related to COVID-19, work is anticipated to begin during the fourth quarter of 2020.

$40 per barrel and an exchange rate of 1.35 Canadian dollars to one U.S. dollar.” data-reactid=”71″ type=”text”>All figures in U.S. dollars, unless otherwise noted. Gold equivalent figures for 2020 operating guidance are based on a gold-to-silver ratio of 74:1. Cash costs and capital expenditures guidance is based on an oil price of $40 per barrel and an exchange rate of 1.35 Canadian dollars to one U.S. dollar.

USA, Turkey, Canada, and Argentina, combined with a global pipeline of high-quality development and exploration assets in the USA, Turkey, Mexico, Peru, and Canada. In 2019, the four operating assets produced over 720,000 ounces of gold and 7.7 million ounces of silver. ” data-reactid=”73″ type=”text”>SSR Mining Inc. is a leading, free cash flow focused intermediate gold company with four producing assets located in the USA, Turkey, Canada, and Argentina, combined with a global pipeline of high-quality development and exploration assets in the USA, Turkey, Mexico, Peru, and Canada. In 2019, the four operating assets produced over 720,000 ounces of gold and 7.7 million ounces of silver. 

Battle Mountain–Eureka trend in Nevada, USA; the Seabee mine along the Trans-Hudson Corridor in Saskatchewan, Canada; and  the Puna mine along the Bolivian silver belt in Jujuy, Argentina. SSR Mining has an experienced leadership team with a proven track record of value creation. Across SSR Mining, the team has expertise in project construction, mining (open pit and underground), and processing (pressure oxidation, heap leach, and flotation), with a strong commitment to health, safety and environmental management. ” data-reactid=”74″ type=”text”>SSR Mining’s diversified asset portfolio is comprised of high margin, long-life assets along several of the world’s most prolific precious metal districts including the Çöpler mine along the Tethyan belt in Turkey; the Marigold mine along the Battle MountainEureka trend in Nevada, USA; the Seabee mine along the Trans-Hudson Corridor in Saskatchewan, Canada; and  the Puna mine along the Bolivian silver belt in Jujuy, Argentina. SSR Mining has an experienced leadership team with a proven track record of value creation. Across SSR Mining, the team has expertise in project construction, mining (open pit and underground), and processing (pressure oxidation, heap leach, and flotation), with a strong commitment to health, safety and environmental management. 

SSR Mining intends to leverage its strong balance sheet and proven track record of free cash flow generation as foundations to organically fund growth across the portfolio and to facilitate superior returns to shareholders.

SSR Mining is listed under the ticker symbol SSRM on the NASDAQ and the TSX, and SSR on the ASX.

Edward Farid, Executive Vice President, Chief Corporate Development Officer ” data-reactid=”78″ type=”text”>F. Edward Farid, Executive Vice President, Chief Corporate Development Officer 

Michael McDonald, Director, Corporate Development & Investor Relations ” data-reactid=”79″ type=”text”>Michael McDonald, Director, Corporate Development & Investor Relations 

[email protected]
Phone: +1 (888) 338-0046 or +1 (604) 689-3846″ data-reactid=”80″ type=”text”>SSR Mining Inc. 

E-Mail: [email protected]

Phone: +1 (888) 338-0046 or +1 (604) 689-3846

www.ssrmining.com. ” data-reactid=”81″ type=”text”>To receive SSR Mining’s news releases by e-mail, please register using the SSR Mining website at www.ssrmining.com.

Except for statements of historical fact relating to us, certain statements contained in this press release constitute forward-looking information, future oriented financial information, or financial outlooks (collectively “forward-looking information”) within the meaning of Canadian securities laws. Forward-looking information may be contained in this document and our other public filings. Forward-looking information relates to statements concerning our outlook and anticipated events or results and in some cases, can be identified by terminology such as “may”, “will”, “could”, “should”, “expect”, “plan”, “anticipate”, “believe”, “intend”, “estimate”, “projects”, “predict”, “potential”, “continue” or other similar expressions concerning matters that are not historical facts.” data-reactid=”83″ type=”text”>Except for statements of historical fact relating to us, certain statements contained in this press release constitute forward-looking information, future oriented financial information, or financial outlooks (collectively “forward-looking information”) within the meaning of Canadian securities laws. Forward-looking information may be contained in this document and our other public filings. Forward-looking information relates to statements concerning our outlook and anticipated events or results and in some cases, can be identified by terminology such as “may”, “will”, “could”, “should”, “expect”, “plan”, “anticipate”, “believe”, “intend”, “estimate”, “projects”, “predict”, “potential”, “continue” or other similar expressions concerning matters that are not historical facts.

Forward-looking statements in this press release include statements concerning, among other things: preliminary cost reporting in this document; timing and content of the updated Technical Report; production, cost, and capital expenditure guidance; the results of the merger-of-equals transaction; our near term catalysts; the results of any gold reconciliations; the ability to discover additional oxide gold ore; the generation of free cash flow and payment of dividends; matters relating to proposed exploration; communications with local stakeholders; maintaining community and government relations; negotiations of joint ventures; negotiation and completion of transactions; commodity prices; Mineral Resources, Mineral Reserves, realization of Mineral Reserves, and the existence or realization of Mineral Resource estimates; the development approach; the timing and amount of future production; the timing of studies, announcements, and analysis; the timing of construction and development of proposed mines and process facilities; capital and operating expenditures; economic conditions; availability of sufficient financing; exploration plans; receipt of regulatory approvals; expectations regarding COVID-19, its ongoing impact on us and any interruptions it may cause on our operations; and any and all other timing, exploration, development, operational, financial, budgetary, economic, legal, social, environmental, regulatory, and political matters that may influence or be influenced by future events or conditions.” data-reactid=”85″ type=”text”>Forward-looking statements in this press release include statements concerning, among other things: preliminary cost reporting in this document; timing and content of the updated Technical Report; production, cost, and capital expenditure guidance; the results of the merger-of-equals transaction; our near term catalysts; the results of any gold reconciliations; the ability to discover additional oxide gold ore; the generation of free cash flow and payment of dividends; matters relating to proposed exploration; communications with local stakeholders; maintaining community and government relations; negotiations of joint ventures; negotiation and completion of transactions; commodity prices; Mineral Resources, Mineral Reserves, realization of Mineral Reserves, and the existence or realization of Mineral Resource estimates; the development approach; the timing and amount of future production; the timing of studies, announcements, and analysis; the timing of construction and development of proposed mines and process facilities; capital and operating expenditures; economic conditions; availability of sufficient financing; exploration plans; receipt of regulatory approvals; expectations regarding COVID-19, its ongoing impact on us and any interruptions it may cause on our operations; and any and all other timing, exploration, development, operational, financial, budgetary, economic, legal, social, environmental, regulatory, and political matters that may influence or be influenced by future events or conditions.

You should not place undue reliance on forward-looking information and statements. Forward-looking information and statements are only predictions based on our current expectations and our projections about future events. Actual results may vary from such forward-looking information for a variety of reasons including, but not limited to, risks and uncertainties disclosed in our filings on our website at www.ssrmining.com, on SEDAR at www.sedar.com, on EDGAR at www.sec.gov and on the ASX at www.asx.com.au and other unforeseen events or circumstances. Other than as required by law, we do not intend, and undertake no obligation to update any forward-looking information to reflect, among other things, new information or future events.” data-reactid=”87″ type=”text”>You should not place undue reliance on forward-looking information and statements. Forward-looking information and statements are only predictions based on our current expectations and our projections about future events. Actual results may vary from such forward-looking information for a variety of reasons including, but not limited to, risks and uncertainties disclosed in our filings on our website at www.ssrmining.com, on SEDAR at www.sedar.com, on EDGAR at www.sec.gov and on the ASX at www.asx.com.au and other unforeseen events or circumstances. Other than as required by law, we do not intend, and undertake no obligation to update any forward-looking information to reflect, among other things, new information or future events.

This news release includes Mineral Reserves and Mineral Resources classification terms that comply with reporting standards in Canada and the Mineral Reserves and the Mineral Resources estimates are made in accordance with NI 43-101. NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. These standards differ significantly from the requirements of the SEC set out in SEC Industry Guide 7. Consequently, Mineral Reserves and Mineral Resources information included in this news release is not comparable to similar information that would generally be disclosed by domestic U.S. reporting companies subject to the reporting and disclosure requirements of the SEC. Under SEC standards, mineralization may not be classified as a “reserve” unless the determination has been made that the mineralization could be economically produced or extracted at the time the reserve determination is made.” data-reactid=”89″ type=”text”>This news release includes Mineral Reserves and Mineral Resources classification terms that comply with reporting standards in Canada and the Mineral Reserves and the Mineral Resources estimates are made in accordance with NI 43-101. NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. These standards differ significantly from the requirements of the SEC set out in SEC Industry Guide 7. Consequently, Mineral Reserves and Mineral Resources information included in this news release is not comparable to similar information that would generally be disclosed by domestic U.S. reporting companies subject to the reporting and disclosure requirements of the SEC. Under SEC standards, mineralization may not be classified as a “reserve” unless the determination has been made that the mineralization could be economically produced or extracted at the time the reserve determination is made.

Cautionary Note Regarding Non-GAAP Measures” data-reactid=”91″ type=”text”>Cautionary Note Regarding Non-GAAP Measures

Cash costs and AISC per ounce sold are Non-GAAP Measures with no standardized definition under IFRS. For further information and a detailed reconciliation to IFRS, please see the “Non-GAAP Financial Measures” section of our Management’s Discussion and Analysis dated as of August 6, 2020 filed on SEDAR at www.sedar.com.” data-reactid=”93″ type=”text”>Cash costs and AISC per ounce sold are Non-GAAP Measures with no standardized definition under IFRS. For further information and a detailed reconciliation to IFRS, please see the “Non-GAAP Financial Measures” section of our Management’s Discussion and Analysis dated as of August 6, 2020 filed on SEDAR at www.sedar.com.

Cision

http://www.prnewswire.com/news-releases/ssr-mining-provides-updated-full-year-2020-outlook-of-680-000-to-760-000-gold-equivalent-ounces-at-aisc-of-965-to-1-040-per-ounce-301133748.html” data-reactid=”105″ type=”text”>View original content: http://www.prnewswire.com/news-releases/ssr-mining-provides-updated-full-year-2020-outlook-of-680-000-to-760-000-gold-equivalent-ounces-at-aisc-of-965-to-1-040-per-ounce-301133748.html

SOURCE SSR Mining Inc.

Cision

http://www.newswire.ca/en/releases/archive/September2020/18/c0466.html” data-reactid=”126″ type=”text”>View original content: http://www.newswire.ca/en/releases/archive/September2020/18/c0466.html

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top